"Transforming intricate plans into enduring realities through masterful execution and discipline."

2016


Project Completion

Works Carried Out for MEGPL

Old Maintenance Building Conversion

Galley HVAC Upgrade Works

Mess Hall Feeder Line Works

Installation of Waste Management Shelter

Installation of Transportation Office Canopy

Installation of Warehouse Preservation Area

Container Yard Fencing Project

Installation of Concrete Channel Drain at Level 0

Several Water Leek Repairs in The Facility

Asphalt Repairs

Installation of Concrete Pads for Arc Flash Mitigation T 103, T105

Excavation and Cable Installation at Substation Level 2

Installation of Fire Suppression

Galley HVAC New Drainage System

Galley HVAC Installation of Catchment Basin and 10” line

Removal of IT Building and Foundations

Works Carried Out for Noble Energy / CHEVRON

Construction & Refurbishment of Existing School at Basakato 2015/16

Design, Construction of Foundations and Erecting 6 Mobi Covers 2016

Construction of Foundations and Installation of Shutter Doors on Main Building 2016

Installation of Tie in to Main Sewer Line 2016

Supply Designated Team to carry out Methanol Transfers from Tanks to Boats

Installation of New Fence Around Coms at Pico 2016

Works Carried Out for AMPCO

Supply of Vehicles for TAR

Supply of Scaffold Erectors for Painting Project

TAR Support

Installation of Location Monuments

Drainage Works in North Fire Water Tank Ditches

Entrance Staff Parking Lenel Barrier Installation

Excavating Inspection Pits for New Gexcon Building

Construction of New Laydown Stone Area for Gexcon Building

Cutting and Removal of Large Trees in Gexcon Area

Drainage Works and Re Landscaping for Methanol Tank Bund Area

Supplying Labour to Excavate to Locate Existing Services for Gexcon Project

Surveying Works Throughout Plant and Facility

Installation of Concrete Pad for New RO Tank

Supply of Scaffolding Team

Supply of Insulating Team

To supply plant, Equipment and Manpower for Gexcon Earthworks

To construct New Lift Station

Construction of Three Number Concrete Bunded Area Slabs for Desal Dosing Area

Construction of Concrete Bunded Diesel Transfer Slab

Construction of New Foundations and Slab for Gexcon Building Section F

Construction of Temporary Footpath to Tank 802 A

Construct Concrete Slab Entrance to Duel Fuel Area

Plant Drainage and Re Landscaping in Duel Fuel Area

Construction of New Foundations and Slab for Gexcon Building Section E

Installation of Ducts and Foul Services for Gexcon Building and Temp Offices

Works Carried Out for Ministry of Mines and Hydrocarbons (MMH)

MMH Bome Camp consist of General Maintenance of the Complex & Gardening Services 2016 – Present

Works Carried Out for Hess

Fabrication of Racks in Bome

Supply Security Services in Bome

Removal and Re Installation of Rigging Loft

Construction of Lifting Frames for Welding Machines

Supply of manpower to Erect Racking

Works Carried Out for Bohlen Doyen

Construction of New CNG Bus Station Carpark & V Ditches in Malabo 2016

Construction of New CNG Bus Station Carpark in Bata 2016